Notes
Slide Show
Outline
1
Advanced Nominations for TE, AGT and M&N US
  • Approximate Run Time:  1 Hour


  • To display this tutorial as a full screen presentation, press the “Slide Show” button on the lower right of the screen.



2
Topics Covered
  • Introduction to Segmentation
  • Firm Transport Scheduling Priorities
  • Calculating and Viewing Scheduling Priorities
  • Allocation of Entitlements among Nominations
  • Batch Validation Processes
  • Bumping Rules
  • Pipeline and Meter Operator Cuts
  • Effect of Increasing or Decreasing Nominated Volumes


  • To jump directly to a topic, click on it at this time.  Otherwise, click the left mouse button to go to the next topic.



3
Introduction to Segmentation
Basic Terminology
4
Introduction to Segmentation
Additional Terminology
5
Introduction to Segmentation
6
Introduction to Segmentation
7
Firm Scheduling Priorities
  • Since scheduling priorities vary by pipeline, please click on the Pipeline you wish to review:
  • TET LP
  • AGT
  • M&N US
  • To jump directly to a topic, click on it at this time.  Otherwise, click the left mouse button to go to the next topic.
8
Firm Scheduling Priorities - TE
  • TE has four scheduling priorities for firm transport:
  • In Path Nominations:
  • Priority 1: Firm Receipt Point to Firm Delivery Point
  • Priority 2: Secondary Receipt Point to Firm Delivery Point
  • Priority 3: Any Nomination that Delivers to a Secondary Delivery Point


  • Out of Path Nominations:
  • Priority 4: Transportation contract has flow point entitlements in the zone, but the nomination is outside the path of the contract’s flow entitlements.
9
Firm Scheduling Priorities - TE
  • Priority 1:  Firm Receipt Point to Firm Delivery Point which is in path


  • When a shipper has contractual rights to receive gas from a point, or rights to have gas delivered to a point, then these are defined as firm points.  Looking at it from the pipeline’s standpoint, the pipeline’s obligation to receive gas from a specific point is called the MDRO, or maximum daily receipt obligation.  The pipeline’s obligation to deliver gas to a specific point is called the MDDO, or maximum daily delivery obligation.


  • When (1) gas is being moved from a firm receipt point to a firm delivery point, (2) the quantity of gas being moved is within the MDROs and MDDOs of the points being used, and (3) the nomination to move the gas is within the contract’s path, then that nomination receives a scheduling priority of 1, the highest priority available.


10
Firm Scheduling Priorities - TE
  • Priority 2: Secondary Receipt Point to Firm Delivery Point which is in path


  • When a nomination exceeds the firm entitlements assigned to a receipt point (i.e. the receipt exceeds the MDRO of that point), the excess is classified as a secondary receipt.  If a receipt point never had any firm entitlements assigned to it, then any receipts from that point are classified as secondary.


  • Receipts from a TABS pool are always secondary receipts, since TABS pools are not firm receipt points.


  • When a nomination (1) receives gas from a secondary point, (2) delivers to a firm delivery point, and (3) is within the contract’s path, then that nomination receives a priority 2.


11
Firm Scheduling Priorities - TE
  • Priority 2: Restriction on a Secondary Receipt Point to Firm Delivery Point


  • Normally, gas being moved from a secondary receipt point (such as a TABS pool) to a firm delivery point is ranked as a priority 2.  However, if there is a restriction in a zone which is downstream of the receipt zone, the priority will be increased to a priority 1.


12
Firm Scheduling Priorities - TE
13
Firm Scheduling Priorities - TE
  • Priority 3: Delivery to a Secondary Point which is in path


  • When a shipper delivers gas to a secondary point and the nomination is within path, that nomination is classified as a priority 3 (regardless of whether the receipt point was firm or secondary).


  • For example, for a nomination which is in path, if the shipper does have firm rights to the delivery point (i.e. the shipper has MDDO at a delivery point), but those rights have been exceeded, the excess will be classified as a secondary delivery, scheduled at a priority 3.


  • In addition, for a nomination which is in path, if the shipper does not have any firm rights to the delivery point (i.e. no MDDO), then all the gas delivered to that point will be classified as a secondary delivery, scheduled at a priority 3.


14
Firm Scheduling Priorities - TE
  • Priority 4:  Transport Out-of-Path


  • A nomination is out-of-path when segment entitlements do not exist for any segment in the nomination’s path, or where existing segment entitlements have been exceeded at any point in the path of the nomination.
  • Note that the “firmness” of the receipt or delivery points does not matter.  If the contract on which the shipper is nominating does not have a “firm path” from receipt to delivery point, that nomination is out- of-path, and it is assigned a priority 4.


  • Also, any nomination which runs contrary the flow of the underlying contact is out-of-path.  For example, a backhaul nomination on a forward-haul contract is out-of-path, and will be assigned a priority 4.


15
Firm Scheduling Priorities - TE
16
Firm Scheduling Priorities - TE
17
Firm Scheduling Priorities - TE
18
Firm Scheduling Priorities - TE
  • Impact of Restrictions on Out of Path Nominations – Priority 4A and 4B


  • If a restriction causes a cut to a nomination which is out-of-path, the priority 4 nomination is further classified into priorities 4A and 4B.


  • If the restriction is in that portion of the nomination where the shipper has contract path entitlements, then the priority of the nomination is a 4A.


  • If the restriction is in that portion of the nomination which is out-of-path, the nomination priority is 4B.


19
Firm Scheduling Priorities - TE
  • Impact of Restrictions on Out of Path Nominations – Priority 4A and 4B



20
Firm Scheduling Priorities – Next Section
  • Click on the following button to go to the next section, discussing how to view the priorities assigned to scheduled gas:




  • Click anywhere except on the above button to go to the next topic in this section, which will discuss firm scheduling priorities for AGT.
21
Firm Scheduling Priorities - AGT
  • In Path Nominations:
  • Priority 1: Firm Receipt Point to Firm Delivery Point
  • Priority 2: Receipt or Delivery Point is Secondary


  • Out of Path Nominations:
  • Priority 3: Transport is Out of Path
22
Firm Scheduling Priorities - AGT
  • Priority 1:  Firm Receipt Point to Firm Delivery Point which is in path


  • When a shipper has contractual rights to receive gas from a point, or rights to have gas delivered to a point, then these are defined as firm points.  Looking at it from the pipeline’s standpoint, the pipeline’s obligation to receive gas from a specific point is called the MDRO, or maximum daily receipt obligation.  The pipeline’s obligation to deliver gas to a specific point is called the MDDO, or maximum daily delivery obligation.


  • When (1) gas is being moved from a firm receipt point to a firm delivery point, (2) the quantity of gas being moved is within the MDROs and MDDOs of the points being used, and (3) the nomination to move the gas is within the contract’s path, then that nomination receives a scheduling priority of 1, the highest priority available.


23
Firm Scheduling Priorities - AGT
  • Priority 2: Receipt or delivery point is Secondary, In Path


  • A point which does not have any contractual receipt or delivery entitlements (i.e. no MDRO or MDDO at that point) is classified as a secondary point.  In addition, when firm entitlements at a receipt or delivery point are used up (that is, when the MDRO or MDDO of the points are exceeded), any further flow through that point is classified as secondary.
  • When one of the points in a nomination is secondary, then the nomination is a priority 2.  When a portion of the nomination exceeds any of the point’s firm entitlement’s rights (that is, when receipts exceed MDRO or deliveries exceed MDDO), then that portion of the gas flow which exceeds firm entitlements is secondary, and that portion is scheduled at a priority 2.


  • This assumes that the nomination is in-path – i.e. there are sufficient segment flow entitlements between receipt and delivery points for the quantity of gas transported.
24
Firm Scheduling Priorities - AGT
  • Priority 3:  Transport Out-of-Path


  • A nomination is out-of-path when segment entitlements do not exist for any segment in the nomination’s path, or where existing segment entitlements have been exceeded at any point in the path of the nomination.
  • Note that the “firmness” of the receipt or delivery points does not matter.  If the contract on which the shipper is nominating does not have a “firm path” from receipt to delivery point, that nomination is out- of-path, and it is assigned a priority 3.


  • Also, any nomination which runs contrary the flow of the underlying contact is out-of-path.  For example, a backhaul on a forward-haul contract is out-of-path, and will be assigned a priority 3.


25
Firm Scheduling Priorities - AGT
26
Scheduling Priorities – Next Section
  • Click on the following button to go to the next section, discussing how to view the priorities assigned to scheduled gas:




  • Click anywhere except on the above button to go to the next topic in this section, which will discuss firm scheduling priorities for M&N US.
27
Firm Scheduling Priorities – M&N US
  • In Path:
  • Priority 1: Firm Receipt Point to Firm Delivery Point
  • Priority 2a: One point is secondary.
  • Priority 2b: Both points are secondary.


  • Out of Path:
  • Priority 3a: One point is firm.
  • Priority 3b: One point is secondary within path.
  • Priority 3c: Both points are secondary, out of path.


28
Firm Scheduling Priorities – M&N US
  • Priority 1: Firm point receipt to firm delivery point


  • When a shipper has contractual rights to receive gas from a point, or rights to have gas delivered to a point, then these are defined as firm points.  The contractual right to receive gas from a specific point into the pipeline is called the MDRO, or maximum daily receipt obligation.  The contractual right to have gas delivered from the pipeline to a specific point is called the MDDO, or maximum daily delivery obligation.


  • When (1) gas is being moved from a firm receipt point to a firm delivery point, (2) the quantity of gas being moved is within the MDROs and MDDOs of the points being used, and (3) there are sufficient segment entitlements at each segment along the nomination’s path, then the nomination receives a scheduling priority of 1, the highest priority available.


29
Firm Scheduling Priorities – M&N US
  • Priority 2a: Between a Firm and a Secondary Point within transportation path


  • A point which is used as a receipt or delivery point which does not have any firm contractual entitlements (i.e. no MDRO or MDDO at that point) is classified as a secondary point.  In addition, when firm entitlements of a receipt or delivery point are used up (that is, when the MDRO or MDDO of the points are exceeded), any further flow through these points are classified as secondary.


  • When only one of the points in the nomination is secondary, then the nomination is a priority 2a.  When a portion of the nomination exceeds the point’s firm entitlement rights (that is, when receipts exceed MDRO or deliveries exceed MDDO), then that portion of the gas flow which exceeds firm entitlements is secondary, and that portion is scheduled at a priority 2a.


  • Note that this assumes that the nomination is in-path – i.e. there are sufficient segment flow entitlements between receipt and delivery points.


30
Firm Scheduling Priorities – M&N US
  • Priority 2b: Between Two Secondary Points within transportation path


  • When both points in the nomination are secondary, then the nomination is a priority 2b.  When a portion of the nomination exceeds the point’s firm entitlement’s rights for both the receipt and delivery points (that is, when receipts exceed MDRO and deliveries exceed MDDO), then that portion of the gas flow which exceeds firm entitlements at both receipt and delivery points is a priority 2b.


  • This assumes that the nomination is in-path – i.e. there are sufficient segment flow entitlements between receipt and delivery points.
31
Firm Scheduling Priorities – M&N US
  • Priority 3a:  Primary Receipt to Out-of-path Delivery, or Out-of-path Receipt to Primary Delivery


  • When gas is moving between a primary point and a secondary point which is out-of-path,  then the priority of that nomination is 3a.  For example, gas moving from a primary receipt point to a secondary delivery point which is out-of-path will be a priority 3a.  Also, gas moving from a secondary receipt point which is out-of-path to a primary delivery point will also be a priority 3a.




32
Firm Scheduling Priorities – M&N US
  • Priority 3b:  Secondary In-Path Receipt to out-of-path Delivery, or Out-of-path Receipt to Secondary Delivery


  • When gas is moving between a secondary point which is in-path and a secondary point which is out-of-path,  then the priority of that nomination is 3b.  For example, gas moving from a secondary receipt point which is in-path to a secondary delivery point which is out-of-path will be a priority 3b.  Also, gas moving from a secondary receipt point which is out-of-path to a secondary delivery point which is in-path will be a priority 3b.




33
Firm Scheduling Priorities – M&N US
  • Priority 3c:  Out-of-path Receipt to out-of-path Delivery


  • When gas is moving between a secondary receipt point which is out-of path to a secondary delivery point which is out-of-path, then the priority of that nomination is 3c.


  • In addition, any time segment entitlements between a receipt and delivery point are missing, or those entitlements have been used up, then the priority of that nomination will be a 3c.  This is true regardless of the status of the receipt and delivery points.  For example, if a nomination moves gas from a firm receipt point to a firm delivery point, but there are insufficient segment entitlements between the two points, then the priority of that nomination will be a 3c.
34
Firm Scheduling Priorities - M&N US
35
Calculating Firm Scheduling Priorities
36
Calculating Firm Scheduling Priorities
37
Calculating Firm Scheduling Priorities
38
Calculating Firm Scheduling Priorities
39
Calculating Firm Scheduling Priorities
40
Calculating Firm Scheduling Priorities
41
Calculating Firm Scheduling Priorities
42
Calculating Firm Scheduling Priorities
43
Viewing Firm Scheduling Priorities
44
Viewing Firm Scheduling Priorities
45
Viewing Firm Scheduling Priorities
46
Allocation of Entitlements
  • Flow entitlements will be allocated to nominations based on two factors:  First, delivery ranking; and second, time of nomination entry. If two or more activities have the same delivery ranking, then time of entry for these activities will be used to allocate entitlements.  Time of entry will be determined by the last, or latest volume entered in an activity’s receipt of delivery quantity field.


  • If activities are not ranked, the default delivery ranking of 999 will apply to all activities, and flow entitlements will be allocated solely on the time a volume was entered in an activity’s receipt or delivery quantity field.


  • Flow entitlements allocated to each activity will then be used to determine each activity’s scheduling priority.
  • The following slides illustrate these principles.


47
Allocation of Flow Entitlements
48
Allocation of Flow Entitlements
49
Allocation of Flow Entitlements
50
Allocation of Flow Entitlements
51
Allocation of Flow Entitlements
52
Allocation of Flow Entitlements
53
Allocation of Flow Entitlements
54
Allocation of Flow Entitlements
55
Allocation of Flow Entitlements
56
Allocation of Flow Entitlements
57
Batch Validation Processes
  • Two sets of batch processes will run on a preset schedule every day.  They are:


  • 1. Timely Batch Process
  • 2. Hourly Batch Processes


  • While either of these batch processes are running, nominations which are being validated and scheduled will not be available for update.  They can be viewed, but if a shipper tries to update one of these "locked" nominations by pressing the submit key from the nomination or confirmation screen, a message will display stating that the nomination is being used by another process.


  • The following screens provide more detail about the nature and timing of these processes.
58
Timely Batch Process
  • The first major category of batch processes is the timely batch process.  This process takes timely nominations, incorporates a wide array of information affecting pipeline capacity (such as demand, restrictions, and so forth), and determines which nominations can be satisfied for the next full gas day.


  • As the name implies, the scheduling of the timely batch process is driven by the timely deadline of 11:30 AM.  At approximately 12:05 PM every day, the timely batch process will begin, and examine timely nominations so that the pipeline can be scheduled for the next gas day.


  • The timely batch process should take about 40 minutes, but that can vary depending on pipeline conditions.


59
Hourly Batch Validation Process
  • The second category of batch processes will be the hourly validation processes.  These processes will run at the top of the hour, every hour.  These batch processes will perform several essential functions, such as:


  • Validate MDQ of all activities under all related releasing and replacement contracts
  • Apply confirming party and scheduling cuts
  • Schedule nominations
  • Assign scheduling priorities
  • Pull in late and intraday nominations
  • Validate nominations which should match (such as Storage nominations and Zone balance transfers)



60
Hourly Batch Validation Processes
  • 5 minutes before the execution of the hourly validation processes, a warning message will display to inform users of the upcoming run.


  • The hourly validation processes will validate all late and intraday nominations.  Like the daily process, when the hourly batch validation processes are running, late and intraday nominations will not be available for update.


  • In order to allow for the completion of the timely batch process, the hourly processes will not begin picking up late nominations for the next gas day until 2PM.
  • Finally, note that intraday nominations cannot be entered during the last hour of the gas day (i.e. after 8 AM for the gas day ending at 9 AM).
61
Chart of Batch Validation Processes
62
Hourly Validation Processes
63
Reduction Results Screen
64
Bumping Rules
65
Chart of Bumping Rules
66
Two Categories of Gas Cuts
  • First, there are the cuts made by the timely and hourly batch validation processes. These cuts will be based on scheduling priority, nomination delivery ranking, and time of entry.


  • Second, there are operator cuts, or cuts by meter confirming parties.  These will be automatically processed based on nomination rankings only.
67
Cuts by Pipeline:
Scheduling v. Curtailment
68
Timing of Scheduling v. Curtailment
69
Scheduling v. Curtailment
70
Pipeline Cuts - Backhauls
71
Confirming Party Meter Cuts
72
Confirming Party Meter Cuts
73
Confirming Party Meter Cuts
74
Confirming Party Meter Cuts
75
Confirming Party Meter Cuts
76
Confirming Party Meter Cuts
77
Confirming Party Meter Cuts
78
Confirming Party Meter Cuts
79
Confirming Party Meter Cuts
  • Meter confirming parties can only reduce gas volumes - they cannot increase them.
  • If a meter confirming party cuts the volume of scheduled gas, the only way to reinstate the original volume is to have the shipper re-nominate.


80
Changing Nominations
  • If a nomination is reduced after the timely deadline, it will retain its original time of entry (i.e. the time the last quantity was typed into either the receipt or delivery quantity fields).  For example, if the original nomination was entered as a timely nomination, the reduced volume will also be treated as a timely nom.


  • However, if a nomination is increased, the time of entry assigned to the nomination will be updated.  If the nomination is changed after the timely deadline, that portion of the nomination which represents an increase will be considered a late nomination, and be scheduled accordingly.  The original portion of the nomination will retain its original time of entry.
81
Recap
  • Introduction to Segmentation
  • Firm Transport Scheduling Priorities
  • Calculating and Viewing Scheduling Priorities
  • Allocation of Entitlements among Nominations
  • Batch Validation Processes
  • Bumping Rules
  • Pipeline and Meter Operator Cuts
  • Effect of Increasing or Decreasing Nominated Volumes